Projects

9
Projects

Autumn sale campaign

At risk

Smrekar Pohištvo d.o.o. · Next: Campaign launch, Wed 19 Aug

49 hplanned for 19.5 h of open work people do · 2 people

Open work covered56%

8.5 h not planned

3 tasks have nobody booked before the due date: Approve the final ad creatives · Results report template for the client. Drag across the person's row below, or use Assign someone.

2 over capacity

Luka and Ana: switch the board to People to see what else they carry.

Campaign launch in 6 days

Every bar ends by then. The line on the board marks the date.

Board

The same plan as Planning. Drag a bar to move it, drag its end to change it, drag across an empty row to add one.

ConfirmedTentativeLeaveConflict
Campaign launch
August 2026
September 2026

M

10

T

11

W

12

T

13

F

14

S

15

S

16

M

17

T

18

W

19

T

20

F

21

S

22

S

23

M

24

T

25

W

26

T

27

F

28

S

29

S

30

M

31

T

1

W

2

T

3

F

4

S

5

S

6

Autumn sale campaignSmrekar Pohištvo d.o.o.49 h planned of 31 h estimated
LKLuka Kovač
3hAutumn sale campaign
AZAna Zupan
5hAutumn sale campaign

Drag across an empty stripe to schedule work · drag a bar to move it · drag either end to change the dates · click a bar to edit it · hatched bands are approved or requested leave.

Open work people do

Agent work needs no hours on the board. For the rest: is the person responsible booked before it is due?

MN0.5 h leftMon 11 AugNot planned
LK0 h leftTue 12 AugPlanned
AZ4 h leftTue 12 AugPlanned
LK4 h leftMon 18 AugPlanned
AZ3 h leftFri 15 AugPlanned
–6 h leftFri 5 SepNo owner
MN2 h leftThu 11 SepNot planned